Kudrytskyi said dozens of small cogeneration units, usually around 5 MW each, were delivered to small towns, especially in Rivne and Zhytomyr oblasts. He said local budgets in towns of 10,000 to 30,000 people generally cannot afford the roughly UAH15 million ($340,000) needed to connect them.
“The energy ministry cuts a ribbon, posts on Facebook that, through extraordinary, unbreakable, powerful efforts by the government and the ministry, another 5 MW have been delivered to a given town — and washes its hands of the rest,” Kudrytskyi said.
“These units, to be clear, mostly still just sit somewhere, unconnected and not operating in the power grid.”
Kudrytskyi warned the idle equipment is deteriorating while consumers suffered 16 to 20 hours of power cuts a day this past winter. He said there is still no consolidated, reliable state-level inventory of the donated units.
“Often a report says a unit is 'ready to operate,' and 'ready to operate' only means it has been delivered. There is no [grid] connection, and sometimes no connection plan, no project-estimate documentation,” he added.
Kudrytskyi also criticized misleading statements about
deployment progress. He recalled that the Energy Ministry said in September
2025 that 2,300 MW of decentralized generation was operating in the system, but
after a change of ministers the figure was revised down to little more than 600
MW.